The following is an intriguing timeline of events that
surround Kit and Stuart Sutherland’s acquisition of the unit adjacent to their
own that curiously unfolded at precisely the same time GIL homeowners found themselves
the only ones left at the dinner table when the nearly $200,000 tab was delivered for a construction defect
that no one – not even the developer – argued they should have to pay for. No one, except Stuart Sutherland, that is.
HOW IT CAME TO BE
02/19/01
Kit and Stuart
Sutherland purchase 660 Glen Iris Dr, NE, Unit 409 (their primary unit) for $342,000, of which $273,600
was financed via a conventional mortgage obtained from First Union Mortgage
Corp.29
05/30/02
While the Glen Iris
Board was still under developer control, Jerrold Miller, of Miller-Gallman
Developers – the developer of Glen Iris Lofts – appoints Kit Sutherland to the
GIL Board of Directors publicly at a Glen Iris Lofts homeowners meeting. The Board then consisted solely of Jerrold Miller,
W. Bruce Gallman and Kit Sutherland.
“Kit Sutherland of Phase I was
appointed to the current Board of Directors by Jerry Miller and Bruce Gallman”1
At the same homeowners’
meeting that Miller announced Kit’s appointment to the first homeowner Board,
Miller acknowledges responsibility of the slope stabilization project when he
responds to a homeowner question on the subject.
“Homeowner
question for Jerry Miller:
3. What are we doing about the
landscape at the rear of the building that washes away when it rains?
The
landscape architects have been assigned to examine the erosion and give a plan
of correction to us.”1
10/02/02
In a meeting with the GIL Board of Directors, developer Jerry Miller again openly acknowledges responsibility for correcting the slope stabilization problem behind the Phase II building.21
02/11/03
At the Annual Meeting,
held at 7:00 PM, Stuart Sutherland voted by proxy for Ellen Hines - the owner of the
unit adjacent to their own that they would buy the following year.
06/04/03
Sandy Jones, the first
President of the homeowner-controlled GIL Board, sends an e-mail requesting
Gary Caruso, an engineer with Criterium-Caruso Engineers, to perform a forensic
study of the failed retaining wall to determine if the developer should have
taken steps to shore up rear retaining wall.2
06/12/03
In a noteworthy halt to
the momentum to build the case that the Miller-Gallman should be held
accountable for correcting the failed retaining wall, the GIL Board minutes
note that it has decided to take the Erosion Engineering Control Study off the
table for the time being.
“Bid for Erosion Control and Next
Steps (Kit and Sandy) Kit will you please bring the letter from Craig Howell?
Erosion
Engineering Control study is taken off the table”3
GIL Board votes to
approve a special assessment to fund the slope stabilization project, although
the amount of the assessment will later prove to be only about one-tenth the
amount eventually required to remedy the problem.3 (Continued...)
06/13/03
Beginning of period
during which GIL Board meeting minutes are missing from the files maintained by
Community Management Associates and the GIL Board and are likewise not among
those made available to homeowners on the Glen Iris Intranet. During this period, Sandra Jones announces
that she has been transferred by her employer, GE and will be resigning her
position as Board President and refined cost estimates and discussions
regarding the responsibility for the retaining wall failure were discussed by
members of the GIL Board.23
10/08/03
Kit and Stuart
Sutherland refinance 660 Glen Iris Dr, NE, Unit 409 with a loan from the Lowry
mortgage network for $245,00029 – possibly due to an average decline
in interest rates of 1.125% from the time of their original loan was taken out
in 2001.30
01/08/04
The availability of GIL
Board meeting minutes resumes.
Board member Ritsa
Zaharis provided an update on the slope stabilization project.
“Erosion Control Project
Ritsa gave an update on the
status of the permitting efforts and other activity on this Project.”4
Kit and Stuart Sutherland obtain a second mortgage
note on 660 Glen Iris Dr, NE, Unit 409 for $162,700 ‘cash out’ from Wachovia
Bank, for a combined property encumbrance of approximately $407,700. Fulton County Tax Assessors Office placed the
value of the property for 2004 at $317,300.28 After the closing of this financial
transaction, Kit and Stuart Sutherland have $162,700 in cash – just $2,300 more
than what is later required to purchase the loft adjacent to their primary
residence, 660 Glen Iris Dr, NE, Unit 409, several months later.28
01/22/04
The GIL Board continues
to work on the slope stabilization project with Mike Beecham - the GIL property
manager with Piedmont Management Associates, the management company used by GIL
at the time.
“Erosion Control Project
Mike Beecham reported on the
status of the permit application and other action items. He will continue to
work with Scott Reno.”5
01/26/04
Board
determined that their initial cost estimates of correcting the failed retaining
wall were less than a quarter of what they estimate to be the cost as of
January 22, 2004. At this time, the
Board determined that construction of a replacement wall will not be sufficient
and that a ‘stepped’ or terraced approach must be pursued and, as a result, the
cost estimate is revised dramatically upward to $75,000 to $125,000. After that announcement, several Board
members raised the possibility of pursuing a legal route to force the developer
to pay for what he had already accepted responsibility to remedy and that
engineers had determined was a defect of construction. Stuart Sutherland “argued” that this approach
“would not be cost effective”. Board
decides to work further with engineers to refine a plan to more definitively
address the slope stabilization plan of action.8
“4. Erosion Control Project
Update
• Scott Reno gave the board
members an update of the situation of the retaining back wall. Various
solutions were outlined. The original "retaining wall" idea will not
suffice. Instead a stepped slope will be pursued, given the slope of the back wall.
• The repair is very costly. The
assessment of last year will not be enough, it will roughly be 1/4 of the total
cost of the project. We are waiting for true estimate, but it may be in the
range of $75,000 to $120,000. To our advantage, this project can be done in
phases.
• Some BOD members discussed
about the possibility of pursuing a legal route to get the developer to pay for
this project. It was argued that it will not be cost effective.
• In a month the Board will know
better. It will receive an accurate plan that that can be sent back to the
engineers to come up with a proposal. Then the Board can make a decision and
get bids.”6
01/27/04 to 04/21/04
During this time, GIL
Board decides to terminate its management contract with Piedmont Management
Associates and selects Community Management Associates (CMA), although there is
no mention of any discussion regarding this decision in the GIL Board meeting
minutes. The first text in Board meeting
minutes that evidences the prior decision is found in the meeting minutes for
May 26, 2004 (see timeline date, below).
04/22/04
David Hildebrand, a
structural engineer and President of Hildebrand Engineers that was hired by the
GIL Board to help develop a plan to develop a plan to terrace the slope,
confirms that it is a problem that must be addressed.
“Scott Reno led a discussion of
the erosion control project. David Hildebrand, the Association's engineer, has
provided an outline of the project. Mike Beecham has sent an RFP to three
vendors, one of whom was recommended by David and two of whom are known to
Mike. David will help with the permitting once we have chosen a contractor.”7
05/26/04
Scott Reno
presented several bids for consideration by the Board so that the slope
stabilization project can finally move forward.
There is no mention that any of the proposals are outside the prior
estimated cost range of $75,000 to $120,000.8 Although the issue was never mentioned in any
prior Board meeting minutes, the Board had also, apparently, already decided to
sign a management contract with Community Management Associates (CMA).
“The BOD discussed putting the
battery backup project on CMA's early
list.
Bids received for back wall”8
06/15/04
Although the transition of Association records and
other responsibilities to CMA had only just begun, the GIL Board abruptly
decided to relieve Scott Reno of all slope stabilization project
responsibilities and, instead, handed them over to Michele Richards, GIL’s
newly assigned property manager.
“Michele will take over the
project to fix the erosion problem. Scott will provide her with all the
information she needs. She will start by getting more information on the bids
and to evaluate financing alternatives.”9
Additionally, the Board of Directors voted to approve
the May, 2004 Board meeting minutes with the provision that, for the May
minutes and going forward, the vote of any particular Board member would be
removed from the minutes, as one Board member (presumably Stuart Sutherland,
the only attorney on the Board at the time) advised that there was “no need to
include this information”.
III. Approval of May Minutes
• May minutes were approved by
the board. The only comment was to remove details on how each Board member
voted on specific topics. No need to include this information.9
07/20/04
Ms. Richards, our CMA property manager, presents the
Board with a new proposal (dated 7/13/04) for the slope stabilization project
submitted by her ‘recommended’ vendor - Good Earth Environmental - one that is
substantially higher than all other estimates – at $200,000. However, the building permit that would later
be filed with the City of Atlanta states that the total project cost is only
$165,000. (Note: When submitting a building permit application to the City of
Atlanta, the applicant is required to provide a sworn statement attesting to
the accuracy of the stated project cost, and failure to state a true project
cost can result in serious financial penalties as well as a revocation of the
offending party’s ability to obtain future building permits for work inside the
City limits). The GIL Board votes to
approve the Good Earth Environmental proposal, as “recommended” by Ms. Richards. Ms. Richards also presents a proposal from National
Cooperative Bank (NCB) obtained by CMA for the project’s financing. (Note: Although the meeting minutes indicate
that the Good Earth Environmental proposal is attached to the meeting minutes,
no such information was, in fact, attached).
“Michele recommends the Board to
move forward with the bid by GoodEarth Environmental. The Board approved to
accept this bid for Slope Stabilization from GoodEarth Environmental (bid
attached to the Agenda)”10
“Regarding financing of the
project, Michele presented to the Board the Financing Proposal from NCB. The
Board analyzed the proposal and approved a motion to secure a loan with NCB for
$200,000 on a five year fixed rate. This money will be used to pay for the
retaining wall slope stabilization project.”10
10/15/2004
Although the unit was not listed in FMLS (First Multiple
Listing Service) at the time, Kit and Stuart purchase 660 Glen Iris Dr, NE,
Unit 408 for a stated price of $160,500 from Atlanta philanthropists and investors
Samuel Hines (a former professional basketball player, currently retired, age
41)26 and Ellen Hines (admitted to the Georgia Bar in 1992, full-time
practicing attorney for four years, ending with King & Spalding in 1997,
currently of counsel for Unisys Corporation, Blue Bell, Pennsylvania, age 45).25
The Hines’ own or have owned units in both Miller-Gallman developments located at 660 (Glen Iris Lofts, Ph I) and 650 (Ponce Springs Lofts) Glen Iris Dr, NE as investors. None of the units purchased in Miller-Gallman properties were ever owner-occupied (the Hines’ $850,000 Alpharetta home is pictured, below).28
The sale price of unit 408 was 5% less than the average price per square foot of all other Glen Iris Lofts sales transacted during the three months leading up to and three months following the sale date and about 6% less than the average price per square foot of all other Glen Iris Lofts sales transacted during the 45 days on either side of that sale date.28 After the settlement of the sale, 80% of the stated purchase price was later financed via a conventional mortgage obtained from ABNAmro in the amount of $128,400.29
10/22/2004
Building permit is issued for the failed rear retaining wall
behind 640 Glen Iris Dr, NE at a stated project cost of $165,000.24
12/15/2004
When questioned about the Board’s decision to obtain
financing to pay for the slope stabilization project rather than charge a special
assessment, Stuart Sutherland stated that it was the Board’s determination that
the amount of the special assessment would be too burdensome.22 Further, when asked by homeowners why no
action was ever pursued against the developer to remedy the failed retaining wall
behind Phase II, Stuart Sutherland stated that ‘they’ (unclear who was meant by
‘they’) felt it was better to “remain on his (Jerry Miller’s) good side, should
we need his help with any other problem down the road”.22 This stated reason given by Stuart Sutherland was
different than the one he provided to
members of the Board of Directors on 1/26/2004 when he stated that the reason the
developer should not be pursued to foot the bill for the wall’s failure was
because doing so “would not be cost effective”.
CONCLUSION While
it was certainly not illegal for Stuart Sutherland to purchase the unit
neighboring his own (Ph I, 408), the facts surrounding that purchase raise
important issues of ethics and open the door to a plausible accusation of self-dealing.
- It is clear that the owners of unit 408 (Mr. & Mrs.
Hines) had a professional relationship with the developer, Jerry Miller, as
they were investors that bought in early in more than one of his developments.
- It is also clear that the Sutherlands had some prior relationship
with the Hines’ as well, given that they (the Sutherlands) knew the Hines’ well
enough for Ellen Hines to give Stuart Sutherland voice authorization to sign on
her behalf for the proxy for unit 408 that he voted at the 2003 Annual
homeowners’ meeting.
-Unit 408 was not listed for sale when it was sold.
-It is highly unlikely that at the time of the sale, the
owners of 408 would have been motivated to sell merely because they needed
their investment principal returned to them, as they never listed the unit for
sale and Mr. & Mrs. Hines – both of whom were only in their mid-thirties at
the time – were already retired and quite wealthy, choosing to spend most of their
time engaged in philanthropic endeavors.
- Despite the fact that the unit was not – and had never
been – for sale, the Sutherlands suddenly undertake an effort to purchase unit
408 (Ph I) at precisely the time the Board is contemplating legal action
against the developer for the failure of the rear retaining wall to the tune of
nearly $200,000.
- It is an established fact that the Sutherlands look upon
the transfer of ownership of other loft units at Glen Iris as possible bargaining
chips in the negotiation of settling legal matters affecting the Association, according
to an e-mail authored by Kit Sutherland herself in 2002.31
- Wide swaths of missing Board minutes and, presumably,
Stuart’s recommendation to the Board to discontinue record keeping regarding
individual Board members’ votes on specific issues leading up to the Board’s
determination that GIL homeowners and not
the developer should foot the $200,000 bill for the retaining wall project,
would not support the conclusion that there was “nothing to hide” with respect
to his actions on the matter.
- While not a significant fact itself, the purchase of unit
408 at a 5%-6% discount compared to other sales transacted for Glen Iris Lofts
around the same time, certainly would not
support any claim that the transaction was conducted at an arm’s length.
- The fact that the reason Stuart Sutherland provided as
justification for his advice that the Association should not take legal action against the developer for the nearly $200,000
homeowners ended up paying to partially resolve the problem (water run-off
behind Phase II still continues to be a problem, despite all the money spent to
correct it, thus far, that will need to be addressed anew at some future date) to
Glen Iris Lofts Board members was different
than the reason he later provided to homeowners would indicate the possibility
that neither reason was truthful.
- The fact that the Association did have a very strong case against the developer regarding his
culpability in remedying the failed wall – based on numerous statements by
Jerry Miller himself that he would fix the problem and the determination by two professional engineering firms that
the slope was too steep to begin with and constituted a construction defect – yet
it was advised against doing so by
Stuart Sutherland constitutes the most damning evidence of all that the Sutherlands
possibly stood to gain financially were Stuart’s ill-advised
advice relied upon. At the very least, Stuart Sutherland should have advised the GIL Board that it should seek the advice of the law firm GIL had on retainer at the time - Weismann, Nowack, Curry & Wilco - as to whether or not a legal action against Miller-Gallman was advisable. He did not.
-Stuart Sutherland never
disclosed to the Glen Iris Board that he was negotiating to purchase unit
408 from a business associate of Jerry Miller during the time he was advising
the Board not to take legal action against
Jerry Miller.
It is not
possible to know if the Sutherlands ended up paying all, some or none of the
funds used to buy unit 408. Nor does it
really matter. The issue is that Stuart
Sutherland should not have been playing both sides of the fence. On one hand he is negotiating with the
developer or developers associates to obtain property of considerable value for
himself, while on the other hand he is purporting to be acting in the best
interests of the Association when he counsels the Association against taking action that would cause
financial harm to at least one member of the party with whom he is negotiating
for his own financial betterment.
But as is always the case, a lot can be learned from the way
things eventually pan out. Jerry
Miller side-stepped a nearly $200,000 tab that he otherwise most likely would
have had to pay (plus legal expenses), the Sutherlands ended up getting a good
deal (at the time) on the unit adjacent to theirs and GIL homeowners got stuck
paying for a $200,000 project that no one
– including the developer himself – felt it was their responsibility to pay for
– solely as a consequence of the advocacy and actions of one person, and one person only – Stuart Sutherland.
*******************************
SOURCES CITED
1Minutes of
the Glen Iris Homeowners Meeting held May 30, 2002 that can be found on the
Glen Iris Intranet: http://intranet.glenirislofts.com.
2E-mail from
Sandra Jones to Mike Beecham and copied to Kit and Stuart Sutherland, dated
June 4, 2003 that can be viewed at: http://glenirislofts.blogspot.com/2011/12/boards-hot-pursuit-of-200k-from.html#more
3Minutes of
the Glen Iris Board of Directors meeting held June 12, 2003 that can be found
on the Glen Iris Intranet: http://intranet.glenirislofts.com
4Minutes of
the Glen Iris Board of Directors meeting held January 8, 2004 that can be found
on the Glen Iris Intranet: http://intranet.glenirislofts.com
5Minutes of
the Glen Iris Board of Directors meeting held January 22, 2004 that can be
found on the Glen Iris Intranet: http://intranet.glenirislofts.com
6Minutes of
the Glen Iris Board of Directors meeting held January 26, 2004 that can be
found on the Glen Iris Intranet: http://intranet.glenirislofts.com
7Minutes of
the Glen Iris Board of Directors meeting held April 22, 2004 that can be found
on the Glen Iris Intranet: http://intranet.glenirislofts.com
8Minutes of
the Glen Iris Board of Directors meeting held May 26, 2004 that can be found on
the Glen Iris Intranet: http://intranet.glenirislofts.com
9Minutes of
the Glen Iris Board of Directors meeting held June 15, 2004 that can be found
on the Glen Iris Intranet: http://intranet.glenirislofts.com
10Minutes of
the Glen Iris Board of Directors meeting held July 20, 2004 that can be found
on the Glen Iris Intranet: http://intranet.glenirislofts.com
21See page 4 of meeting minutes attached to the Blog post at: http://glenirislofts.blogspot.com/2011/12/developer-acknowledges-responsibility.html
22Meeting
notes by homeowners in attendance Steven Sharp (Ph II, 501) and Chris Gordon (Ph. II, 611)
23Minutes of
the Glen Iris Lofts Board of Directors, mentioned subsequent to 6/13/2003
24City of
Atlanta Bureau of Buildings, permitting
25Martindale-Hubbell
www.martindale.com/Ellen-K-Hines/864484-lawyer.htm
26Up with
Kids Sports, Inc. Web site www.myuwks.com
27RealtyTrac
28Fulton
County Tax Assessors Office
29CoreLogic data
compiled from public and private sources
30MortageX.com
Web site, historical mortgage rate table
31E-mail from Kit Sutherland to Sandra Jones, dated 11/29/02
that can be found at: http://www.scribd.com/doc/79101644/You-Gotta-Watch-Your-Back-When-Kits-Your-Friend
Hello Glen Iris People,
ReplyDeleteHere is a little more information for you. Almost 2 weeks ago I called the board and texted a picture of a breach under the concrete retaining wall. I asked if they would call me so we could talk about this. And as you guessed they never did.
This is a big problem and could be a very expensive problem if it docent get fixed asap! Tonight it is raining and again were have the erosion and soil from our neighbors property flowing onto our property and into our storm sewers again.
If we have a big enough rain the breach under that concrete wall "could" take out a good section of the terraced retaining wall and again covering the parking lot in mud. This is VERRY expensive.
In board meetings the last few years I have suggested that if they were going to do more planting that we add more plant stabilization to the terraced retaining wall area, especially in the same area we had repaired a few years ago.
Again, to the board members that read this blog, THIS IS WHAT I DO FOR A LIVING, give me a damn call back so we can discuss this problem!
Scott Reno, out (for now)
Scott-
DeleteThank you for alerting everyone to this problem...Is there anything that can be done temporarily and quickly to possibly keep the wall from being breached in the current rain storm? Would it help if some of us were to go get 30 or 40 bags of gravel from HD to fill in at the top where there is erosion - just as a temporary stop gap measure?
This is in reply to the Utility cart issue: F%&*ing ridicules!! They will send us a security alert email about a additional utility cart wich actually helps us(come on a "recording device?), but they will not let us know when our cars have been burglarized!! WTF? They really are INSANE!! We have got to do something! I am not sure how much longer I can put up with this dictatorship
ReplyDeleteThe duration of the 'dictatorship' would be shortened were you to send us an e-mail at gil@go.to Looking forward to hearing from you...
Delete-Peace